EGP Critical Path Visualizer
Folder: 00108-EGP-Critical-Path-Visualizer
Version: 1.0
Date: April 5, 2026
Author: Betty Suarez, Chief of Staff
Initiative: EGP PRBoost Alpha Launch
Overview
Interactive dashboard visualizing dependency chains, blockers, and milestone status for the EGP PRBoost Alpha Launch. Designed for internal deployment via Google Sites.
Overall Status: AT RISK
Days to Alpha: 1 (April 6, 2026)
P0 Blockers: 5 active
Chain Completion: 38%
Section 1: Critical Path Diagram
Chain 1: Website Gate
| Step |
ID |
Description |
Status |
| 1 |
P0-001 |
Weak CTA |
Blocked |
| 2 |
P0-003 |
Hierarchy Diagram |
Blocked |
| 3 |
P0-005 |
No Urgency |
Not Started |
| 4 |
P0-006 |
Brand Quality |
Not Started |
| 5 |
GATE-002 |
Website Go/No-Go |
Overdue |
Flow: P0-001 > P0-003 > P0-005 > P0-006 > GATE-002
Chain 2: Email Infrastructure
| Step |
ID |
Description |
Status |
| 1 |
EMAIL-001 |
Sender Identity Setup |
Complete |
| 2 |
EMAIL-002 |
Postmaster Registration |
Complete |
| 3 |
EMAIL-003 |
Email Warm Verification |
In Progress |
| 4 |
EMAIL-004 |
Day 1 Send (100 emails) |
Not Started |
Flow: EMAIL-001 > EMAIL-002 > EMAIL-003 > EMAIL-004
Chain 3: Prospect Pipeline
| Step |
ID |
Description |
Status |
| 1 |
PIPE-001 |
POTM/BOL Daily Scan |
In Progress |
| 2 |
PIPE-002 |
Email Verification |
In Progress |
| 3 |
PIPE-003 |
MDM Gold Load |
Not Started |
| 4 |
PIPE-004 |
CRM Sync |
Not Started |
| 5 |
PIPE-005 |
Email Queue |
Not Started |
| 6 |
PIPE-006 |
Send |
Not Started |
Flow: PIPE-001 > PIPE-002 > PIPE-003 > PIPE-004 > PIPE-005 > PIPE-006
Chain 4: Alpha Launch Milestones
| Step |
ID |
Description |
Status |
| 1 |
GATE-001 |
NO-GO (Mar 14) |
Overdue |
| 2 |
ALPHA-001 |
Soft Alpha Bypass |
In Progress |
| 3 |
ALPHA-002 |
Day 1 Send (Apr 6) |
Blocked |
| 4 |
ALPHA-003 |
Week 1 Review |
Not Started |
| 5 |
GATE-002 |
Website Re-Review |
Not Started |
Flow: GATE-001 > ALPHA-001 > ALPHA-002 > ALPHA-003 > GATE-002
Section 2: Milestone Timeline
| Date |
Milestone |
Status |
| March 14 |
GATE-001 NO-GO |
Overdue (issued) |
| March 30 |
Soft Alpha Target |
Missed |
| April 5 |
TODAY |
Current |
| April 6 |
Alpha Launch (Day 1 Send) |
Tomorrow |
| April 9 |
EMAIL-004 Willemena Deadline |
Upcoming |
| TBD |
GATE-002 Website Re-Review |
Not Scheduled |
Section 3: Blocker Registry
| ID |
Blocker |
Status |
Owner |
Dependency |
Target |
Impact |
| P0-001 |
Weak CTA on landing page |
Blocked |
Web Studio |
None |
Apr 5 |
Blocks P0-003, GATE-002 |
| P0-003 |
Service hierarchy diagram missing |
Blocked |
Design |
P0-001 |
Apr 6 |
Blocks P0-005, GATE-002 |
| P0-005 |
No urgency messaging |
Not Started |
Content |
P0-003 |
Apr 7 |
Blocks P0-006, GATE-002 |
| P0-006 |
Brand quality below threshold |
Not Started |
Brand |
P0-005 |
Apr 8 |
Final gate to GATE-002 |
| GATE-001 |
Website Go/No-Go (NO-GO issued) |
Overdue |
CDAIO |
All P0 items |
Mar 14 |
Triggered soft alpha bypass |
| EMAIL-003 |
Email warm-up verification pending |
In Progress |
Infrastructure |
EMAIL-002 |
Apr 5 |
Blocks Day 1 send |
| PIPE-003 |
MDM Gold Load not started |
Not Started |
Data Ops |
PIPE-002 |
Apr 5 |
Blocks CRM sync and send |
Section 4: Initiative Progress
| Initiative |
Progress |
Status |
| EGP PRBoost Alpha Launch |
35% |
At Risk |
| Infrastructure |
72% |
On Track |
| Automations |
45% |
In Progress |
| Customer Acquisition |
28% |
Behind |
| Customer Retention |
15% |
Early Stage |
Section 5: Daily Checklist (April 5, 2026)
- [x] Sender identity configuration verified (EMAIL-001, EMAIL-002) -- DONE
- [ ] Complete email warm-up verification (EMAIL-003) -- P0 CRITICAL
- [ ] Run POTM/BOL daily scan (PIPE-001) -- P0 CRITICAL
- [ ] Email verification via verification platform (PIPE-002) -- P0
- [ ] MDM Gold Load (PIPE-003) -- P0 BLOCKED by PIPE-002
- [ ] Resolve P0-001 Weak CTA -- P0 BLOCKED
- [ ] Pre-flight check: 100 email queue loaded and validated -- TONIGHT
- [ ] Confirm soft alpha bypass authorization (ALPHA-001) -- EOD
Color Code Legend
| Color |
Meaning |
| Green |
Complete |
| Blue |
In Progress |
| Orange |
Blocked |
| Red |
Overdue |
| Gray |
Not Started |
Technical Notes
- Self-contained HTML file (no external dependencies)
- CSS flow diagram with nodes and arrows (no libraries required)
- Interactive left-side navigation with scroll tracking
- Clickable checklist items for status toggling
- Responsive layout with mobile fallback
- EGP dark theme applied throughout
- Deployable to internal Google Sites via embed
Changelog
| Version |
Date |
Author |
Change |
| 1.0 |
2026-04-05 |
Betty Suarez |
Initial build. PRBoost Alpha Launch critical path. |
www.enroutegrowthplatform.io | CustomerSuccess@EnRouteGrowthPlatform.io | +1.866.891.2779
(c) 1991-2026 EnRoute Growth Platform. All rights reserved.
00108-EGP-Critical-Path-Visualizer | Generated by Betty Suarez, Chief of Staff