EnRoute Growth Platform

EGP Critical Path Visualizer

EGP INTERNAL — Not for external distribution

EGP Critical Path Visualizer

Folder: 00108-EGP-Critical-Path-Visualizer
Version: 1.0
Date: April 5, 2026
Author: Betty Suarez, Chief of Staff
Initiative: EGP PRBoost Alpha Launch


Overview

Interactive dashboard visualizing dependency chains, blockers, and milestone status for the EGP PRBoost Alpha Launch. Designed for internal deployment via Google Sites.

Overall Status: AT RISK
Days to Alpha: 1 (April 6, 2026)
P0 Blockers: 5 active
Chain Completion: 38%


Section 1: Critical Path Diagram

Chain 1: Website Gate

Step ID Description Status
1 P0-001 Weak CTA Blocked
2 P0-003 Hierarchy Diagram Blocked
3 P0-005 No Urgency Not Started
4 P0-006 Brand Quality Not Started
5 GATE-002 Website Go/No-Go Overdue

Flow: P0-001 > P0-003 > P0-005 > P0-006 > GATE-002

Chain 2: Email Infrastructure

Step ID Description Status
1 EMAIL-001 Sender Identity Setup Complete
2 EMAIL-002 Postmaster Registration Complete
3 EMAIL-003 Email Warm Verification In Progress
4 EMAIL-004 Day 1 Send (100 emails) Not Started

Flow: EMAIL-001 > EMAIL-002 > EMAIL-003 > EMAIL-004

Chain 3: Prospect Pipeline

Step ID Description Status
1 PIPE-001 POTM/BOL Daily Scan In Progress
2 PIPE-002 Email Verification In Progress
3 PIPE-003 MDM Gold Load Not Started
4 PIPE-004 CRM Sync Not Started
5 PIPE-005 Email Queue Not Started
6 PIPE-006 Send Not Started

Flow: PIPE-001 > PIPE-002 > PIPE-003 > PIPE-004 > PIPE-005 > PIPE-006

Chain 4: Alpha Launch Milestones

Step ID Description Status
1 GATE-001 NO-GO (Mar 14) Overdue
2 ALPHA-001 Soft Alpha Bypass In Progress
3 ALPHA-002 Day 1 Send (Apr 6) Blocked
4 ALPHA-003 Week 1 Review Not Started
5 GATE-002 Website Re-Review Not Started

Flow: GATE-001 > ALPHA-001 > ALPHA-002 > ALPHA-003 > GATE-002


Section 2: Milestone Timeline

Date Milestone Status
March 14 GATE-001 NO-GO Overdue (issued)
March 30 Soft Alpha Target Missed
April 5 TODAY Current
April 6 Alpha Launch (Day 1 Send) Tomorrow
April 9 EMAIL-004 Willemena Deadline Upcoming
TBD GATE-002 Website Re-Review Not Scheduled

Section 3: Blocker Registry

ID Blocker Status Owner Dependency Target Impact
P0-001 Weak CTA on landing page Blocked Web Studio None Apr 5 Blocks P0-003, GATE-002
P0-003 Service hierarchy diagram missing Blocked Design P0-001 Apr 6 Blocks P0-005, GATE-002
P0-005 No urgency messaging Not Started Content P0-003 Apr 7 Blocks P0-006, GATE-002
P0-006 Brand quality below threshold Not Started Brand P0-005 Apr 8 Final gate to GATE-002
GATE-001 Website Go/No-Go (NO-GO issued) Overdue CDAIO All P0 items Mar 14 Triggered soft alpha bypass
EMAIL-003 Email warm-up verification pending In Progress Infrastructure EMAIL-002 Apr 5 Blocks Day 1 send
PIPE-003 MDM Gold Load not started Not Started Data Ops PIPE-002 Apr 5 Blocks CRM sync and send

Section 4: Initiative Progress

Initiative Progress Status
EGP PRBoost Alpha Launch 35% At Risk
Infrastructure 72% On Track
Automations 45% In Progress
Customer Acquisition 28% Behind
Customer Retention 15% Early Stage

Section 5: Daily Checklist (April 5, 2026)


Color Code Legend

Color Meaning
Green Complete
Blue In Progress
Orange Blocked
Red Overdue
Gray Not Started

Technical Notes


Changelog

Version Date Author Change
1.0 2026-04-05 Betty Suarez Initial build. PRBoost Alpha Launch critical path.

www.enroutegrowthplatform.io | CustomerSuccess@EnRouteGrowthPlatform.io | +1.866.891.2779
(c) 1991-2026 EnRoute Growth Platform. All rights reserved.
00108-EGP-Critical-Path-Visualizer | Generated by Betty Suarez, Chief of Staff